  • The North western section of the diversion closest to 219 should now be completed by 29/1/2020.
  • The South western section of the diversion outside no 39 to 210 - the aim is to carry this out between 30/1/2020 and 12/02/2020.
  • From 13/2/20 to 5/3/20 the South eastern section of the diversion works will be coned off - closest to the Fruit and Vegetable stall.
  • Work to complete the new parking bays is programmed to take place between 13/2/2020 and 27/3/2020 with two way traffic flowing after 05/03/2020.

If anyone has further comments, suggestions or queries, please contact Chartway Group on 01622 740140 and speak to Dan Sutton, Site Manager or you can contact Chartway Group using the address on the bottom of the letter attached.